Chronicle of the Atman Data Center expansion

29.01.2021
Company news

In May 2020 we started the construction of a new colocation facility at Atman Data Center Warsaw-1.

Building F6 with an area of 3,027 sq m gross (1,440 sq m net) will have 5 floors and 6 server chambers. It is designed for data center purposes, so it will be equipped with modern security, air conditioning and fire protection systems, as well as 3.6 MW guaranteed IT power supply and emergency power supply systems.

Track the progress of our work, which we update on a regular basis.

June 2020. Beginning of the construction works. Walls and ceilings of the lowest floors are created.
.06
July 2020. Continuation of work on the lowest floors.
.07
August 2020. We are already working on the reinforcement of the second floor, which has an increased total load capacity of 25kN/m2.
.08
September 2020. Work is underway on the 4th floor, where the future data rooms of our clients will be located.
.09
October 2020. The fourth floor is about to finish. Works on the F6 building are proceeding according to the schedule.
.10
November 2020. The F6 ceiling takes shape. Soon, the shell of the building will be a fact and we will move to the next stages of construction.
.11
December 2020. The customary topping out is now on F6. The rooms for our clients take shape. The building is scheduled for completion at the turn of Q2 and Q3 2021.
.12
January 2021. Construction works are going according to schedule.
.01
February 2021. Indoor works are in progress.
.02
March 2021. F6 rooms are gradually filled with technical installations.
.03
April 2021. The F6 building has its final appearance. The technical platform is being built on the roof and the interior is equipped with further technical installations.
.04
May 2021. The interior fitting of the F6 building is in progress...
.05
June 2021. Intensive installation work is underway. In the F6 building we install, among others, fire and air conditioning systems.
.06
July 2021. Installation works inside the building are progressing according to schedule.
.07
August 2021. The F6 building is equipped with all necessary installations for final acceptance.
.08
September 2021. The investment has been completed! The F6 building was put into use for all existing and new customers.
.09